PU Booster - 0,28kg

Login to view prices
Delivery time: 1-3 Business Days
  • Compatible with PU Design
  • Can be mixed with the PU Design resin and hardener mixture
  • Application temperature: minimum 15 °C and maximum 25 °C
  • PU Booster consumption for the total quantity of PU Design (A, B and additive): 0.280kg PU Booster for 20.4 kg PU Design
  • Reduces curing time when used at the specified consumption volume
  • Scope of delivery: PU Booster

Instructions for Use

chevronBottom

Prepare substrate:

The substrate must be levelled, load-bearing, dry, sufficiently tensile and compressive strength, and clean. Dust, oil, grease and release agents must be removed in advance by suitable measures (preferred method: shot blasting; alternatively diamond grinding with thorough vacuum extraction).
Application temperature: 15-25 °C (room and substrate temperature) with a maximum relative humidity of 70 %.

Apply EP Primer:

  1. For mixing, add the entire contents of EP Primer component B into the container of EP Primer component A and mix slowly and thoroughly with a drill for approx. 3 minutes at 300-400 rpm. Working Time: approx. 40 minutes at 20 °C.
  2. Immediately after mixing, pour the material onto the floor, spread it with a rubber squeegee and then roll over it to achieve an even surface while maintaining the floor texture.
  3. Protect the area from moisture, dust and mechanical stress during curing. Walkable after approx. 14 hours, fully loadable after approx. 7 days (temperature-dependent).
  4. Further coating with other products may be applied at 20 °C no earlier than 14 hours and no later than 36 hours after applying the EP Primer. 
    Important: If further coating is not applied within 36 hours, the EP Primer must be broadcast with quartz sand while still fresh/liquid (recommended quantity: approx. 300 g/m²). Before further coating, loose excess quartz sand must be removed with a broom.

If required: Level unevenness (surface roughness) greater than 1 mm with EP Levelling Compound:

  1. For mixing, add the entire contents of EP Levelling Compound component B and 10 kg of quartz sand into the container of EP Levelling Compound component A and mix slowly with a drill for approx. 3 minutes at 300-400 rpm. Working Time: approx. 30 minutes at 20 °C.
  2. Immediately after mixing, pour the mixture onto the floor, spread evenly with a floor squeegee and then deaerate with a spiked roller to achieve an even surface and a smooth finish.
  3. Protect the area from moisture, dust and mechanical stress during curing. Walkable after approx. 15 hours, fully loadable after approx. 7 days (temperature-dependent).
  4. Further coating with PU Design may be applied at 20 °C no earlier than 15 hours and no later than 36 hours after applying the EP Levelling Compound. 
    Important: If PU Design is not applied within 36 hours, the EP Levelling Compound must be broadcast with quartz sand while still fresh/liquid (recommended quantity: approx. 500 g/m²). Before applying the PU Design coating, loose excess quartz sand must be removed with a broom.

Apply PU Design with PU Booster:

  1. Brieftly pre-mix the PU Design A-component. Then, add the entire contents of PU Design component B, 2 × 100 g of EP colour paste, and 400 g of additives into the container of PU Design component A and mix for approx. 40 seconds until a homogeneous mixture is obtained.
  2. Add the PU Booster to the homogenous mixture and mix slowly with a drill for approx. 2 minutes at 300-400 rpm. Transfer the mixture into another mixing container and mix briefly again.
  3. Immediately after mixing, pour the material onto the floor and spread it evenly using a surface squeegee. Then go over it with a rubber squeegee to create the design.
  4. Protect the area from moisture, dust and mechanical stress during curing. Walkable after approx. 3 hours at 20 °C, fully loadable after approx. 4 days (temperature-dependent).
     The PU Finish may be applied at 20 °C no earlier than 3 hours and no later than 36 hours after application of the PU Design. 
    Important: If PU Finish is not applied within 36 hours, the cured layer of PU Design must be sanded until it is completely matt (white haze) before the PU Finish can be applied.
Working TemperatureWalkable / recoatable after
15 °C4 hrs.
20 °C3 hrs.
25 °C2 hrs.

Optional: Apply PU Finish for a matt finish:

  1. For mixing, add the entire contents of PU Finish component B into the container of PU Finish component A and mix thoroughly.
  2. Immediately after mixing, apply the mixture evenly to the floor with a roller to achieve a homogeneous surface while maintaining the floor texture. To achieve a streak-free result, roll first against the direction of the light and then wet-on-wet in the direction of the light source. 
    Pro tip: For an even, homogeneous finish, we recommend 2 coats. The waiting time between coats is at least 16 hours at 20 °C.
  3. Protect the area from moisture, dust and mechanical stress during curing. Walkable after approx. 16 hours, fully loadable after approx. 4 days (temperature-dependent).

Important Notes

chevronBottom

Overdosing the PU Booster can lead to a loss of strength or sticky surface. Underdosing can prolongs the curing time. Never use at temperatures below 15 °C or above 25 °C. The incorporation of air caused by excessive mixing time must be avoided. Colour deviations are possible due to raw material variations. For different batches, base components should be pre-mixed. UV radiation and weather influences may cause slight colour changes.

Attention

chevronBottom

Nocif en cas d'ingestion. Peut provoquer une allergie cutanée. Provoque une sévère irritation des yeux. Risque avéré d'effets graves pour les organes (indiquer tous les organes affectés, s'ils sont connus) à la suite d'expositions répétées ou d'une exposition prolongée (indiquer la voie d'exposition s'il est formellement prouvé qu'aucune autre voie d'exposition ne conduit au même danger). Toxique pour les organismes aquatiques, entraîne des effets néfastes à long terme. Les informations sur l’étiquette du produit doivent toujours être suivies.

piktogram-fisch-ausrufezeichen-giftlunge.png